Period: 10/17/2016 – 10/21/2016
Hours to Date: 35
Accomplishments for October 21, 2016
- Engineers submitted their Preliminary Design Document.
- Created & updated the Change Management Plan.
- Created & updated the RACI Chart.
- Created Organization Chart.
- Spoke with Courtney.
- Updated the schedule.
- Met with engineers.
Goals for October 3-7, 2016
- Finalize the Project Charter and receive engineers’ signatures.
- Finalize the Scope Document and receive engineers’ signatures.
- Update the schedule.
- Continue editing our Risk Management plan, Quality Management plan, and Change Management plan.
- Help engineers organize their website.
Issues:
- Engineers did not follow through with the responsibilities they agreed to fulfill; schedule was uprooted again.
- One of our PMs is still MIA.
- Still not enough cooperation between the PMs and engineers.