MIS 3535 Weekly Progress Report 4/14

From: Turks and Caicos

To: MC Martin

Subject: Weekly Progress Report – April 14, 2019

Period: 04/08/19 04/14/19

Hours:  6    Hours to Date: 48

Accomplishments for week ending April 14, 2019

  • Drafted Risk Management Plan
  • Completed Data Schema
  • Completed RACI
  • Completed Scenarios

Goals for week ending April 21, 2019

  • Begin design of final deliverables
  • Plan binder layout
  • Complete prototype
  • Film use-case videos

Issues:

  • No issues at this time