Weekly Progress Report – 10/28

19 Responses to Weekly Progress Report – 10/28

  • Met with Courtney and received feedback on our Risk Management and Change Management documents. Plan to meet with our BAs on Friday to discuss prototyping and other documents.

  • From: Kevin Santoni, Andrew Fiss – Dairy Download
    To: Mart Doyle, Tony Messina
    Subject: Weekly Progress Report
    Date: October 28, 2016
    Period: 10/24/2016-10/28/2016
    Hours: 2
    Hours to Date: 16
    Accomplishments:
    1. The schedule is almost up-to date, but still needs more work.
    2. Andrew met with Lauren to get our weekly update on her research.
    Goals for Next Week:
    1. Schedule a meeting with Lauren.
    2. Continue working on the schedule.
    3. Continue to revise documents.
    4. Finish the charter.
    Issues:
    None this week.

  • Team Members: Elijah Jamison, Robert Lesnick, Jerald Kahn
    Accomplishments:
    1. Rob and Eli collaborated on the project schedule, and are preparing the final schedule
    2. Myself and Rob met with Courtney on the phone Monday, 10/24 and discussed way to to get the BAs to start producing deliverables
    3. Myself and Eli met with Courtney on the phone Monday, 10/17
    4. I Reviewed my documentation with Courtney before class (risk directory, quality management, stakeholder list, RACI, communication plan)
    5. Rob met with the BA’s on Thursday afternoon and helped them come up with a plan to start producing a final solution
    6. Scheduled remaining appointments with Courtney
    Goals:
    1. Schedule project status meeting with the BAs for next week
    2. Schedule a Documentation QA session for the following week
    3. Schedule a prototype QA session for two weeks out
    4. Finalize the stakeholder list, organizational chart, risk directory
    5. Write written sections of risk management and quality management plan
    6. Post final version of project schedule

  • Team Members: Stephanie Cheng, Jonathan Holland, Jacky Wong
    Period: 10/24/2016-10/28/2016
    Hours: 5
    Hours to Date: 40
    Accomplishments:
    1. Met with Courtney for better feedback on our documentation.
    2. PMs met with each other so we could update the documentation
    Goals for Next Week:
    1. We should have the first look of the prototype for all of the use cases.
    2. We will make sure all the previous documentation is up to date.
    3. Revising management documentations for Courtney to go over.
    Issues:
    1. We still have some questions trying to figure out how to format our documentations

  • Group: Ben, Gino, Alan

    Accomplished:
    1. scheduled meeting with Courtney
    2. followed up with BAs on prototyping

    Goals:
    1. Meet with Courtney
    2. Meet with BAs
    3. Finish fine tuning documents

  • Gallagher, Kevin Vong, Michael Dennis
    To: Anthony Messina
    Period: 10/24/2016 – 10/28/2016
    Accomplishments:
    1. Completed the first draft of our problem statement, project charter and work breakdown structure, organization chart, RACI chart, change management, and Communication plan
    2. Scheduled the rest of our meetings with Courtney.
    3. Started the quality management plan
    4. Have better idea on how to complete the budget.
    Goals for next week:
    1. Go over project with Courtney next week during our meeting.
    2. Finish drafting our project plans that are yet to be completed.
    3. Redo the work breakdown structure.
    4. Get feedback on our project plans that we completed so we can start revisions.

  • From: Brian Wallace, Serena You, Casid Sohou
    To: Tony Messina
    Subject: Weekly Progress Report
    Date: October 28, 2016
    Period: 10/21/2016-10/28/2016
    Hours: 4
    Hours to Date: 24
    Accomplishments:
    1. Met with Courtney via Google Hangout, discussed RACI Chart and Risk Register.
    2. BA’s are starting to focus entirely on prototyping, weekly meetings will be standard to keep them on track.
    3. Completed RACI Chart, Risk Register, Quality Plan, Project Budget, and Stakeholder list.
    Goals for Next Week:
    1. Have a discussion with BAs about early stage prototyping and their vision for the finished product.
    2. Refine our Project Budget and Risk Register. (More detail needed on both)
    3. Meet with Courtney to review current versions of documentation and get tips for managing prototyping setbacks. (Which we expect at some point.)
    Issues:
    1. No current issues. Right now we are more concerned with future setbacks in the prototyping process.

  • From: Lavin Group D (Leor Capunitan, Thomas Lee, and Tyler Gaber)
    To: Anthony Messina
    Subject: Weekly Progress Report – October 28th, 2016
    Period: 10/22/16 – 10/28/16
    Hours: 35 Hours to Date: 35

    Accomplishments for October 28th, 2016
    1) Submitted Quality Assurance Report to Courtney
    2) Submitted Risk Registry Report to Courtney
    3) Met with BAs to discuss current progress on project

    Goals for November 4th, 2016
    1) Finish project schedule for review
    2) Finish project budget for review
    3) Review BA’s project prototype for critique
    All three of these are the same as we continue to work towards finishing the project

    Issues:
    1) BAs have yet to begin their prototyping process and need to begin it immediately
    2) Test this week makes it difficult to focus on anything else but that

  • From: Lavin Group D (Leor Capunitan, Thomas Lee, and Tyler Gaber)
    To: Anthony Messina
    Subject: Weekly Progress Report – October 28th, 2016
    Period: 10/22/16 – 10/28/16
    Hours: 35 Hours to Date: 35

    Accomplishments for October 28th, 2016
    1) Submitted Quality Assurance Report to Courtney
    2) Submitted Risk Registry Report to Courtney
    3) Met with BAs to discuss current progress on project

    Goals for November 4th, 2016
    1) Finish project schedule for review
    2) Finish project budget for review
    3) Review BA’s project prototype for critique
    All three of these are the same as we continue to work towards finishing the project

    Issues:
    1) BAs have yet to begin their prototyping process and need to begin it immediately
    2) Test this week makes it difficult to focus on anything else but the test

  • My partner and I have started working on the scope, budget, project schedule, and risk registry report. We also met with Courtney and discussed our current worries and plans for our project. Our goal for next week is to compete the rough drafts of the previously mentioned documents we started work on.

  • Team Sara Tony and Phil.
    Weekly Progress Report
    Accomplishments this week:
    We had our bi-weekly meeting with Courtney and received great feedback about our documents.
    During Thursday night’s class we presented our quality management plan to the class.
    Plans for this week:
    Meet with PM’s on Monday to begin to revise our documents with the feedback we got from Courtney during the bi-weekly meeting and in-class review.
    Weekly meeting on Wednesday with BA’s to see how their first BA only meeting, Justinmind tutoring, and meeting with professor Lavin went.
    Issues:
    Our BA’s motivational level and if they actually made progress independently of us last week since they cancelled our full team meeting.

  • From: Darpan Patel, Will Agentowicz
    To: Mart Doyle, Tony Messina
    Subject: Weekly Progress Report
    Subject: Weekly Progress Report – October 28th, 2016
    Period: 10/21/16 – 10/28/16
    Hours: 20
    Hours to Date: 20
    Accomplishments:
    1. Finished several deliverables including all Risk Assessment Plan.
    2. Reached out to multiple charities in order to achieve results
    3. Spoke with Project Sponsor to help her re-think development companies
    Goals
    1. Help project sponsor find proper development companies
    2. Continue to contact charities for growing interest in app/website
    3. Help project sponsor stay focused on ultimate goal
    Issues
    1. Engineering student has started to figure out her company, but there are still many obstacles in the way before she is able to dedicate herself to her own company

  • From: Adama Traore, Dario and Michael ( Group B)
    To: Anthony Messina
    Subject: Weekly Progress Report
    Period: 10/21-10/28
    Hours: 5
    Hours to Date: 25
    Accomplishments:
    1) Created a risk registry and change management log
    2) Finished the WBS
    3) Had our Project Charter revised/looked at
    4) Revised our communications plan and quality management plan
    5) Met with Courtney to go over current progress and issue we are facing with the project
    Goals:
    1) Have our budget number correct on our WBS
    2) Have a set weekly meeting with our BAs where people show up
    Issues:
    1) Being able to meet with our BAs on a weekly basis and not just talk through GroupMe/email

  • From: Team 6 (Dan, Wilbert, Tyler)
    To: Anthony Messina
    Subject: Weekly Progress Report – October 28, 2016
    Period: 10/22/16-10/28/16
    Hours: 20 Hours to Date: 85
    Accomplishments for October 21, 2016
    1) Meet with engineers to determine their remaining tasks to confirm that we are still
    on schedule.
    2) Went over documents including WBC, schedule, Project Scope, project charter,
    and budget with team to find areas for improvement.
    Goals for November 4, 2016
    1) Continue to work on draft documents and have other sources, including Courtney
    review them.
    2) Continue to help improve upon project presentation, by trying to set up mock final
    presentation with other teams in the class.
    3) Assist in grip testing that is currently being conducted for the prosthetic hand.
    Issues:
    1) At least one project manager was not able to attend meeting with engineers and
    their faculty advisor this week.
    2) Was not able to meet as an entire group this week, only with project managers and
    engineering team lead.

  • From: Evan Chiao, Jeremy John, Jeff Craskey, Rob Higgins
    To: Mart Doyle, Tony Messina
    Subject: Weekly Progress Report
    Subject: Weekly Progress Report – October 28th, 2016
    Period: 10/21/16 – 10/28/16
    Hours: 5
    Hours to Date: 22
    Accomplishments:
    1. PM team completed drafts of all required documentation.
    2. Gained a better understanding of what the documentation requires per document.
    Goals
    1. Have an extended meeting with BAs next week due to missed meeting this week.
    2. Go over Data Schema and Use Cases with BAs.
    Issues
    1. Couldn’t meet this week due to multiple scheduling issues.

  • From: Jon Kerin, Ben Shaffer
    To: Tony Messina
    Subject: Weekly Progress Report – October 28th, 2016
    Period: 10/21/2016-10/28/2016
    Hours: 15 Hours to Date: 65

    Accomplishments:
    1. Met with all system leads and created finalized WBS hierarchy
    2. Generated cross-system WBS and mapped out dependencies
    3. Established process for tracking resources hours to create budget

    Goals for November 4, 2016
    1. Update MS Project file with new WBS hierarchy
    2. Collect duration, resources, and effort needs for project
    3. Map out dependencies and relationships across phases, activities, and tasks
    4. Outline critical path based on project schedule and dependencies

    Issues:
    1. Behind on critical deliverables
    2. We often need to redo deliverables that we have already created. They don’t properly serve the project as we increase our understanding. The scope has gone through 3 iterations before settling on a refined document. We have also gone through the WBS about 3 times as well, and we are expecting the same for the schedule. We attribute the issue to our inexperience and the scope of the project being so large.

  • Team: Doyle 21
    Accomplished:
    1. Completed our draft start-up budget
    2. Meeting with our sponsor for edits and other suggestions
    Goals for next week:
    1. Make changes to our budget
    2.Work on the WBS, risk and change management plans, and schedule
    3. Redo the quality management plan
    4. Schedule a meeting with Courtney