Weekly Progress Report – 9/30

20 Responses to Weekly Progress Report – 9/30

  • My PM team has finally met with the engineering team on Monday 9/26. The engineering team briefed us on their project. They are making a prosthetic hand with joint movement mimicking the reaction time and strength of a real hand using ninitol alloy which becomes easily manipulated at certain temperatures and returns to their original shape at the opposite extreme. We are currently making a schedule for them to outline their tasks for the upcoming week. The team is currently in the modeling and testing phase with the 3d printed hand to be delivered and assembled by Monday for functional testing.

  • Our team met with Courtney on Monday on web ex and she gave us feedback on how to improve our documents. Budget may need to be reviewed. Charter needs to be worked on. We were able to gather more insight to the project because of interview 2 with Rachel Carr.

  • We will need to discuss project execution as a team.

  • This week our team is meeting on Friday to review their first round of interviews with the TFR division leads to create a draft of the WBS. Each team member was assigned division leaders for each system that they head. Our PMs were strategically placed with individuals whose work was similar. Our team will also revisit the schedule and include a new devision that has come into scope. We have also scheduled five meetings with Courtney over the course of the semester to check our progress.

  • From: Kevin Santoni, Andrew Fiss – Dairy Download
    To: Mart Doyle, Tony Messina
    Subject: Weekly Progress Report
    Date: September 30, 2016
    Period: 09/26/2016-09/30/2016
    Hours: 3
    Hours to Date: 5

    Accomplishments:
    1. Completed the first drafts of our problem statement, project charter, WBS, risk management, communications, quality management, and change management plans.
    2. Created a Google Driver folder and GroupMe chat.
    3. Andrew had a meeting with Courtney.

    Goals for Next Week:
    1. Meet with Lauren to discuss her goals and get a better understanding of what needs to be worked on.
    2. Complete our first draft of the schedule, budget, and scope for the project.
    3. Revise our problem statement, project charter, and WBS.

    Issues:
    1. Was not able to have a team meeting due to conflicting schedules.
    2. We (The PMs) still need more information on what Lauren/Dairy Download wants to accomplish by December.

  • Team Members: Kevin Vong, Robert Gallagher, Michael Dennis
    To: Anthony Messina
    Period: 09/23/2016 – 09/30/2016

    Accomplishments:
    1. Our team completed the first draft of our problem statement, project charter and work breakdown structure.
    2. Currently in the process of drafting our risk management plan, communications plan, quality management plan and change management plan.
    3. Met with Courtney the week prior and she gave us a lot of insight on how to approach the deliverables for our project.

    Goals for next week:
    1. Schedule the rest of our meetings with Courtney.
    2. Finish drafting our project plans.
    3. Get feedback on our project plans so we can start revisions.
    4. Meet up with BA’s to discuss the status of the project and any other issues they may have.

  • From: Evan Chiao, Jeremy John, Jeff Craskey, Rob Higgins
    To: Mart Doyle, Tony Messina
    Subject: Weekly Progress Report
    Date: September 30, 2016
    Period: 09/26/2016-09/30/2016
    Hours: 4
    Hours to Date: 6
    Accomplishments:
    1. Created the first drafts of problem statement, Scope, Charter, WBS, risk management, and communications.
    2. Jeremy held first official meeting with BA’s outside of interviews.
    3. Started activity and uploads to Google Docs, and GroupMe.
    4. Evan and Jeff attended meeting with Courtney to discuss setting the projects foundation, and starting issues.
    Goals for Next Week:
    1. Meet again with team for weekly meeting and get their status updates
    2. Complete the rest of required documentation drafts
    3. Finalize better meeting times
    Issues:
    1. Not everyone could attend meetings due to schedules.

  • We completed our project charter, problem statement, and our scope. We are currently working on the WBS, scheduling, budgets, risk management plan, communications plan, quality management plan and change management plan but have good ideas on what will be on those documents. We need to talk to Courtney again and also have another meeting with our sponsor.

  • Team: Danielle Buerger, Robert Lesnick, Elijah Jamison, Jerald Kahn
    Accomplishments:
    1. Met with Courtney as a team and discussed our project thus far and reviewed documentation
    2. Emailed WBS, Project Charter, and risk management plan to Courtney for feedback
    3. Completed first draft of WBS. Project Charter, and Risk Management Plan

    Plan:
    1. Revise documentation to reflect Courtney’s feedback
    2. Send revised document back to Courtney for feedback
    3. Meet with BA’s a second time to learn about their roles in the project, how their scope is coming along, and how they are managing with the prototyping software
    4. Book a meeting with Courtney for the following week, I believe she’s in Europe next week

  • We completed the rough drafts of our project charter and problem statement, but still need to complete the work breakdown structure. Our goals for next week are to complete the WBS, start on the rough drafts for the risk management, communications, quality management, and change management plans, revise our current documents, and schedule another meeting with Courtney. We also need to schedule a meeting with our project sponsor in order to acquire the necessary information to complete our project plans.

  • Team: Adam Traore, Michael and Dario Trabucco

    Accomplished:

    1. We had a meeting with the BA’s prior to the interview to help craft questions for the interviews
    2. We reviewed the project scope for the BA’s before the final delivery on Thursday.
    3. The project charter and problem statement are done.

    Plan for next week:

    1. We will have the weekly meeting with the BA’s.
    2.This upcoming week we will work on finishing the work-breakdown structure and the project scheduling.
    No major issues so far, all the team members and BA’s are collaborating.

  • From: Lavin Group D (Leor Capunitan, Thomas Lee, and Tyler Gaber)
    To: Anthony Messina
    Subject: Weekly Progress Report – September 30th, 2016
    Period: 9/24/23 – 9/30/16
    Hours:10 Hours to Date: 10

    Accomplishments for September 30th, 2016
    1) Updated Google Drive information with Templates of documents to allow the BAs easy guidelines for document creation
    2) Held second meeting in which we spoke about the project, where we currently stand in the entire semester, the upcoming test, and JustInMind prototyping.
    3) Began working on documentation – WBS and Scope document

    Goals for September 30th, 2016
    1) Begin the budgeting process for the project
    2) Finish the WBS document
    3) Push BAs to start and complete a homepage for their project

    Issues:
    1) BAs have a test on Tuesday which will only give us 3 days to complete a homepage within JustInMind
    2) Even after the 2nd interview, our group still seems to be struggling with the direction of this project

  • Team: Eugene Alan Ben
    This week we accomplished:
    1) we finally met with our BA’s for the first time. I met with them to help them plan out their scope.
    2) Had our first meeting with Courtney to discuss the progress of our project
    3) Began working on documentation WBS and Project charter form

    our goals for next week:
    1) have more contact from our BA’s
    2) finish our WBS and project charter form

  • This week we completed rough drafts of our project scope, project charter and problem statement. We plan on meeting with Courtney as well this week and to meet separately as a group with the engineers. Hopefully we will refine the rough drafts this week as well as complete more deliverable items such as the budget plan, WBS and risk management plan.

  • Team Members: Anthony Vu, Sara Monahan, Phil Tocci
    To: Anthony Messina
    Period: 09/23/2016 – 09/30/2016

    Accomplishments:
    This past week our team was able to complete a first draft of our Project Charter and are continuing to revise it. We also had our weekly PM meeting on Monday to discuss the next steps of a project. We were also able to to contact our BAs to figure out a weekly meeting time to discuss the project. Everyone was able to meet up last week and we were able to critique their scopes in preparation for their next class. On top of all of this, we have set up a Google Drive for our BAs to be able to share their work for us to review. The BAs also had their second interview which some of us were able to attend; they got a lot of useful information from this interview.

    Goals for next week:
    Our team plans to continue to have weekly PM meetings as well as meetings with our BAs. We hope to have drafts of other documentations of the project such as the risk management plan, communications plan, quality management plan, and change management plan. We will also need to schedule our meeting with Courtney, revise our project charter, and help prepare our BAs for the next step of the project.

  • From: Darpan Patel, William Agentowicz – BetYou
    To: Anthony Messina
    Subject: Weekly Progress Report – September 30, 2016
    Period: 09/23/16-09/30/16
    Hours: 2 Hours to Date: 2
    Accomplishments:
    1) Met with Courtney and discussed major issues about project
    2) Completed second draft of WBS and project charter
    3) Began brainstorming tasks for Scope Documents
    Goals for Month Day, 2016
    1) Finish first draft of Scope documents
    2) Complete research regarding charity donations and its feasibility
    3) Complete research on who will be developing website/app
    Issues:
    1) Project sponsor doesn’t seem to understand the goal we have as the project managers
    2) Project sponsor has limited time to work on project along with her classes and work schedule

  • This week our team didn’t meet. We still working on risk management, communication, quality management, and change management plan. Hope we could settle a meeting this week so that we can share our opinions and figure out the details of those four plans for our project.

  • Team: Jacky Wong, John Holland, Stephanie Cheng
    Accomplishment:
    BAs finished 1st draft of the scope, attended the interview and took down notes. Currently working on project statement and started to play around with justinmind.
    PMs worked on Risk Management plan. communications plan, and quality management plan
    Goals for next week is to finish risk management plan communications plan, and quality management plan.
    Plan to start on Change management plan