• Log In
  • Skip to primary navigation
  • Skip to main content
  • Home
  • Syllabus
  • Course Structure
    • Required Texts and Readings
    • Grading and Other Policies
    • Course Schedule
  • Your Instructors
  • Schedule
    • Introduction
    • Online Module One
      • Module One Videos
      • Module One Assignments
        • WA-1.1: Written Assignment 1
    • Online Module Two
      • Module Two Videos
      • Module Two Assignments
        • PA-2.1: Practical Assignment 2
        • WA-2.1: Written Assignment 2
        • PA-3.1: Practical Assignment 3
        • WA-3.1: Written Assignment 3
        • WA-4.1: Written Assignment 4
    • Day One
      • 3/19 AM – Requirements
      • 3/19 PM – Requirements
    • Day Two
      • 3/20 AM – Structured Process Analysis
      • 3/20 PM – Data Analysis
    • Day Three
      • 3/21 AM – Data Modeling
      • 3/21 PM – OO Process Analysis
    • Day Four
      • 3/22 AM – Databases
      • 3/22 PM – Human Factors
    • Day Five
      • 3/23 AM – Implementation & Distributed Systems
      • 3/23 PM – Wrap-Up

Systems and Infrastructure Life Cycle Management

MIS5203

Fox School of Business

PA-2.1: Practical Assignment 2

Be sure to follow the instructions in the Project Management Demonstration for this assignment.

A project has been defined to contain the following list of activities along with their required times for completion.

Activity Number Immediate Activity Time (weeks) Predecessors
1 Collect Requirements 3
2 Analyze processes 2 1
3 Analyze data 2 2
4 Design processes 6 2
5 Design data 3 3
6 Design screens 2 3,4
7 Design reports 4 4,5
8 Programming 5 6,7
9 Test & document 7 7
10 Installation 2 8,9

 

  • Based on this project, create a network diagram, and GANTT chart for this project.
  • Calculate the overall duration of this project, and show the critical path on your network diagram or GANTT chart.
  • What would happen to the project plan if activity 6 were revised with an estimated time of six weeks?
  • Assume that your team is in its first week of the project and has discovered that each of the activity duration estimates is wrong. Activity 2 will take only two weeks to complete. Activities 4 and 7 will each take three times longer than anticipated. All other activities will take twice as long to complete as previously estimated. In addition, a new activity, number 11, has been added. It will take one week to complete, and its immediate predecessors are activities 10 and 9. Adjust the network diagram or GANTT chart, and recalculate the earliest expected completion times.