MIS 3535 Progress Reports

From: Team PMMR

To: MC Martin

Subject: Weekly Progress Report – October 27, 2019 

Period: 10/20/2019 – 10/27/2019

Actual Hours: 

  • Patrick Blewitt: 5 hours
  • Maggie Cameron: 5 hours
  • Monica Webster 5 hours 
  • Raymond Long: 0 hours

Hours to Date: 

  • Patrick Blewitt: 32 hours
  • Maggie Cameron: 30 hours
  • Monica Webster: 33 hours 
  • Raymond Long: 10 hours

Accomplishments for week ending October 27, 2019

  1. Completed the Risk Register
  2. Completed the Change Request Form
  3. Completed Change Management Plan 
  4. Began uploading deliverables to the Website

Goals for week ending November 3, 2019

  1. Upload all deliverables to our project website.
  2. Complete the Status Report
  3. Submit and present project 

Issues:

  1. We have had no communication with Raymond this week. The rest of us have talked in a group-chat but Raymond has not responded.  