Progress Report for the Week ending 3/17

From: Team Blue

To: MC Martin

Subject: Weekly Progress Report  March 17, 2019

 

Period: 03/04/1903/17/19

Hours:  3

Hours to Date: 8

 

Accomplishments for week ending March_17, 2019

1) We developed our first WBS.
2) We started work on our RACI chart.
3) We started work on our Org chart.

 

Goals for week ending March_24, 2019

1) We would like to finish our RACI charts, Org Chart, and Stakeholder Register.
2) We would like to have another meeting with our BAs.